FDE Templates Pack

Handover Runbook

Before the FDE steps back and the customer or support team takes ownership

Download this template (.md) Download all (.zip)

Handover Runbook

System: [name]
Engagement: [customer / project]
Handing over from: [FDE name(s)]
Receiving owner(s): [customer team or support team]
Handover date: [date]
Signed off by: [name, title]

Purpose: give the receiving team everything needed to run, support, and change this system without the FDE in the room. In FDE Framework v0.5, that is the enablement and handoff layer: training by role, a runbook, a named owner, a supervised run, and agreed exit criteria, written at the start of the engagement, not only at the end.

1. What this system does

  • Plain-language description and the business outcome it supports:
  • Users and how they use it:
  • Link to design doc and decision log:

2. Architecture and access

  • Diagram link:
  • Components, where each runs, and who owns each:
  • Integrations (system, method, contact for that system):
  • Access: how to request it, who approves, where secrets are stored
  • Credentials rotated or revoked at handover (list):
  • If a model is used: model version, how version drift is watched, and what replaces the model if the provider retires it

3. Routine operations

TaskFrequencySteps or scriptOwner

4. Monitoring and alerts

  • Dashboards and log locations:
  • Alerts, thresholds, and who receives them:
  • What "healthy" looks like:
  • If a model is used: how operating cost is tracked against the agreed budget

5. Common issues and fixes

SymptomLikely causeFixEscalate if

6. Making changes

  • Where the code and configuration live:
  • How to build, test, and deploy:
  • Change approval process and windows:
  • Known customer-specific customizations and why they exist:

7. Training by role

Operators, engineers, and managers each learn what they need to run, change, or oversee the solution.

RoleWho was trainedMaterialsDate
Operators
Engineers
Managers

8. Supervised run

The customer team operates and changes the solution without help, while the FDE is still there to catch problems.

  • Date and what the customer team operated or changed without help:
  • Issues caught, and how they were fixed:

9. Exit criteria

Agreed at the start of the engagement, not only at the end.

  • Exit criteria agreed with the sponsor, and when:
  • Status of each criterion:
  • Remaining gaps, owners, and due dates:

10. Embed or train (for internal FDEs)

Decide whether the FDE stays embedded, rotates to the next team, or trains the department to run it.

  • Decision:
  • Agreed by:
  • Date:

11. Unwritten knowledge

Workarounds, quirks, and decisions that only exist in someone’s head. Write them here before the FDE leaves. -

12. Support and escalation

  • First responder after handover (named owner):
  • Escalation path and contacts:
  • What the FDE team still covers, and until when:

13. Compliance in operation

FDE Framework v0.5 checkpoint: in operation, with Domains 7 and 11. Check again when a rule changes, or when the use case grows beyond what was approved, for example new product types or new groups of users.

  • Rules and approvals this use case relies on:
  • Accountable owners for use-case sign-off:
  • What to check if a rule changes, or if the use case grows:
  • How AI-use disclosure is kept up to date, if AI is used:

14. Open items

ItemOwnerDue

15. Handover sign-off


Mapped to FDE Framework v0.5: Domains 7, 9, 11; the enablement and handoff layer; and the in-operation checkpoint in the cross-cutting Regulation, Compliance and Responsible AI domain. See https://www.fdecouncil.com/framework/